Sealed Roads Program 2017/18

Category Infrastructure Works Programs
Project Start Date 01/07/2017
Expected Completion Date 30/06/2018
Proponent District Council of Mount Barker
Project Status Current
Contact Work: 08 8391 7290
Email: council@mountbarker.sa.gov.au

Council undertakes a Sealed Roads Works Program throughout the district each year. The list of roads will be updated as the program progresses.

The Mount Barker District Council has a total road network of approximately 805km. This increases every year and consists of approximately 351km of sealed roads, approximately 389km of formed and surfaced roads and approximately 65km of unformed roads.

Council is committed to maintaining all roads in good condition to provide a safe environment with a number of streets and roads scheduled for maintenance during the course of the financial year.   

Works can include tree pruning or removal, drainage improvements and pavement rehabilitation.  Marks may be painted on the road indicating start and finishing points.  Some roads will also have concrete works completed including replacement of kerb and gutter, driveway crossings and spoon drains.

The work will necessitate closing sections of the road for a period of time on the day that construction is undertaken.  During this time there may be limited access to driveway entrances and vehicles should not be left parked on the road.

All endeavours will be made to ensure a minimum of inconvenience, but alternative routes should be planned while these works are under way.  Road users are requested to adhere to any detours that will be in place and plan alternate routes to avoid delay in reaching their destination.

Although work is avoided on the same day as the kerbside bin collection, please ensure bins are out by 6.30am as in most cases these will be emptied before work commences. 

Council endeavours to complete the Sealed Road Works Program within the indicated year, however the program can be subject to change due to unforeseen circumstances. If this occurs the affected segment will be scheduled in a future works program.

 

June 2018

Update - due to wet weather, work is now expected to be complete by 20 June.

Sydney Road shoulder reinstatement works from Bridge Street to Pyrites Road are scheduled to commence on Monday 4th June with completion date of 15th June.  While the Road will be open to traffic, please observe all posted signage for safety of workers and road users.

Contact Downer on Mobile 0407 515 756 For all enquires.

Sydney Road Shoulder Reinstatement Traffic Management Plan(241 kb)

 

May 2018

A temporary full road closure will be in place to facilitate the resurfacing of Sydney Road, Nairne.  The road will be closed to all vehicles (except adjacent property owners) from Timmins Road to Pyrites Road between the hours of 7am to 5pm from 2 May to 8 May 2018.  Detours will be in place.

Sydney Road Nairne Road Closure Detour(1072 kb)

 

 

February/March 2018

Location

Name of Road

Section of Road

Scope of work

Date

Blakiston

Nitschke Road

Full Length

Bitumen spay seal over stone chips

Minor patching 31 January and 1 February

Hahndorf

Ambleside Road

Pain Road to Onkaparinga Valley Hwy

Bitumen spay seal over stone chips

Minor patching 1, 2 & 5 February

Mount Barker

Albert Road

Wellington Road to Alexandrina Road

Asphalt - Deep Lift road renewal (full pavement depth)

 

Nairne

Sydney Road

Recreation Reserve entrance to 100 m west of Pyrites Road intersection

Asphalt – Over lay over existing road surface

 

 

January/February 2018

Frampton Road

Commencement of the works has been delayed due to the lengthy wait to obtain a Network Access Permit from South Australian Power Networks (SAPN) to enable council to excavate around their infrastructure and install drainage pipes.  This is a precursor to road pavement rehabilitation.  It is envisaged that works will be able to recommence from mid-January and be completed in February 2018.

 

Native Avenue

Commencement of the road rehabilitation works has been delayed due to the availability of contract resources and materials.  It is envisaged that works will be able to recommence from mid-January and be completed in February 2018.

 

December 2017

Paech Brothers Road

Construction and bitumen sealing of Paech Brothers Road, Hahndorf – between Balhannah Rd and Ravenswood Lane will commence with tree and roadside vegetation pruning, possible tree removal and drainage improvements in late November and it is envisaged that they will be completed prior to Christmas.

The Road Reconstruction will commence early January and the Bitumen sealing will be carried out in February subject the Bitumen contractor’s availability.

 

November 2017

River Road

On November 9 and 10, line marking will be undertaken on River Road between the hours of 9am and 3pm, between Fairview Road and Kangaroo Reef Road.

As this road has many curves and moderately high traffic for a rural environment, the road will be intermittently closed to facilitate line marking works.

Intermittent closing will involve progressively closing sections of the road for between 10-20 minutes. The road will then be opened to enable the passage of vehicles travelling on this road free of road works.  This approach ensures safety of both road users and Council’s contract staff.

 

September 2017

 

Greenhills-Flaxley Road, Green Hills Range

Downer EDI on behalf of council shall be undertaking road maintenance works on Greenhills-Flaxley Road requiring the road to be closed to traffic between 8 am - 11 am at intersection of Green Hill and Quarry Road on Monday 4 September.

Update:  Due to wet weather, work will be undertaken on 5 September. 

 

Native Avenue, Wistow

Commencement of the works has been delayed from the proposed mid-July date due to the recent storm event and adverse weather.  Now that the conditions are improving, the contractor has indicated that works will be undertaken during September/October providing the weather remains favourable.

 

September Program

Downer EDI on behalf of council shall be undertaking road maintenance works on the following sections of road between 5-11 September weather permitting.

 

Road Name

Description/Location

Suburb

Date Range

River Road

Fairview Rd to Kangaroo Reef Rd

Hahndorf/Mylor

5-8 September

Nitschke Road

Junction Rd to Blakiston Rd

Littlehampton

5-8 September

Green Hill Flaxley Road

Strathalbyn Rd to Quarry Rd – Road closure at Green Hill Flaxley Road and Quarry Road Intersection - 7 am – 11 am 4 September

Harrogate

5 September

Greenhills Rd

300 m East of Whites Road

Meadows

5 September

Mount Barker Caravan Entrance Road

 

Alternative temporary road will be provided

Mount Barker

11 September

Hawthorn Road

300 m south of Bowen Road and 300 m at intersection of Libelt Summer Track

Mount Barker

5-8 September

  

August 2017

Downer EDI on behalf of council shall be undertaking road maintenance works on the following section of road between 21 August and 24 August weather permitting. 

Road Name

Description/Location

Area

Date Works will be undertaken

Greenhills Rd

Quarry Rd to 800 metres west of Quarry Road

Green Hills Range

21-22 August

Whites Rd

Greenhills Rd to 500 metres North of Greenhills Rd

Green Hills Range

21-22 August

Paechtown Rd

Echunga Rd to 800 metres  east of Echunga Rd

Paechtown

22-23 August

 

Downer EDI on behalf of council shall be undertaking road maintenance works on the following section of road between 14 August and 17 August weather permitting.  

Road Name

Description/Location

Area

Date Works will be undertaken

Nottage Rd

Kennett St to Rowley Rd

Meadows

14 August

 

Native Avenue, Wistow

Road maintenance of Native Avenue, Wistow will commence the week of 17 July and is expected to be complete by the end of August, subject to suitable weather conditions.

Works such as tree and roadside vegetation pruning/removal and drainage improvements will be undertaken where required prior to maintenance works.  The maintenance will include the trialling of a new process that uses a bitumen recycling product to better protect the environment and minimise ongoing dust.  

 

July 2017

Downer EDI on behalf of council shall be undertaking road maintenance works on the following section of road between 20 July and 28 July weather permitting. 

Road Name

Description/Location

Suburb

Date Range

River Road

Fairview Rd to Kangaroo Reef Rd

Hahndorf

20-27 July

Nitschke Road

Junction Rd to Blakiston Rd

Littlehampton

21-27 July

Harrogate Road

Military Road to 260 metres south of Doheny Road

Harrogate

24-28 July

 

Downer EDI on behalf of council shall be undertaking road maintenance works on the following section of road between 6 July and 14 July weather permitting. 

Road Name

Description/Location

Suburb

 

Snelling Rd

900 m west of Echunga Road to 2,100 m west of Echunga Road

Hahndorf

6-13 July

Windsor Av

453 m east of Collins St to Martin Rd

Hahndorf

7– 13 July

Ambleside Rd

Pain Rd to Onkaparinga Valley Rd

Hahndorf

10 – 14 July

The maintenance work is in preparation for resurfacing works later in the year.

 

 