North Road Nairne

Category Completed Infrastructure Projects
Project Start Date 23/01/2017
Expected Completion Date 30/06/2017
Proponent District Council of Mount Barker
Project Status Current
Contact Person Infrastructure and Projects
Contact Work: 08 8391 7290
Email: council@mountbarker.sa.gov.au

Further resurfacing is continuing following the installation of staged traffic management devices.

Road Closed for Reconstruction

Following the completion of the drainage works, sections of North Road Nairne will be reconstructed with asphalt from Woodside/Nairne Road to Haeusler Drive together with a further section near Junction Road.

During this time, these sections of North Road will be closed to all vehicles.  Detours will be in place to direct traffic via an alternate route.

Council's contractor has indicated that this work is scheduled for 23 to 27 March from 7am to 6pm. 

 

Further Drainage Work Commencing 14 March 2017

In preparation for the pavement renewal, further drainage improvements will be undertaken along a short section of North Road from Haeusler Drive towards Woodside Road.  This work is scheduled to commence on 14 March and be complete by end of March, subject to suitable weather conditions.

During construction, this section of the west bound lane of North Road will be closed to vehicles.  Detours will be in place to direct traffic via an alternate route to Woodside Road.  

Work Site and Detour Plan North Road Nairne(4070 kb)

 

New Commencement Date

Council's Contractor has advised a new commencement date being 20 February with completion by the 3 March.

Any queries regarding the works on site, please contact:

  • Project Manager – Chris Goold 0418 893 293
  • Site Manager – John Cowley 0400 291 860

 

Drainage

Commencing in late January with completion by late February 2017, concrete works will be undertaken to improve drainage at the following locations:

  • Between Woodside Road and Haeusler Drive – Spoon drain construction across North Road and along North Side of North Road
  • On opposite side of road to Church Street – Mountable kerbing construction and side entry pit construction to collect storm water runoff

During drainage works North Road will remain open to traffic under traffic management.  Please observe all posted signs and traffic control instructions.

Location Plan of Drainage Works

This work is being undertaken in preparation for road improvement works that will be undertaken by the end of the financial year.

 

Previous Traffic Management Projects - North Road Nairne

Information about the traffic management projects is available here:

North Road Traffic Management Stage 1

North Road Traffic Management Stage 2