Henry & Alston Road, Blakiston Stormwater Works

Works will include the installation of a new double stormwater pit, new stormwater pipe and a junction box at the intersection and additional pipe and a new outlet on Alston Road.

Access to roads and properties will be maintained at all times.  Traffic management will be implemented to minimise disruptions during the works.

The contractor will commence in the week beginning 19 May 2014 and works will be undertaken between 7am to 5pm Monday to Friday. It is expected that works will be completed within 2 weeks from commencement subject to weather and any unforseen issues.

Should you require any further information or have any queries as works progress:

  • Civil Works Project Manager, Luke Beltrame, Metro & Country Civil, Mob 0439 681 215. 
  • Council’s Assistant Project Manager, Megan Bonehilll, Mob 0400 301 448