Cameron & Dunn Roads Drainage Works

15 July 2014

Tidy up works have been hampered by inclement weather. There are still one or two days work to be completed when ground conditions are dry.

Before Photo

After Photo

 

March 2014

This project has been scoped to remedy the problem of stormwater flows spilling from Dunn Road across Cameron Road.

Council’s civil contractor, NEO Infrastructure (SA) Pty Ltd, has indicated the start for this project as the week beginning 17th March 2014.

The scope of works includes kerbing on Dunn Road and at the intersection with Cameron Road including spoon drain, new underground stormwater drainage infrastructure and minor pavement and footpath reinstatement associated with the drainage works.

When excavation works commence, a portion of the northern lane of Dunn Road will be closed to through traffic, whilst maintaining access to local residents. Cameron Road will remain under two way traffic conditions with traffic management in place specific to the work zone. Should your property be adjacent to the work zone, you will be given prior notice before any work is undertaken that may temporarily disrupt access to your property.

It is expected that the work will be completed within 6 weeks from commencement subject to weather and any unforseen issues.

  • Civil Works Project Manager, Simon Bowring, (NEO Infrastructure), Mob 0409 119 397
  • Council’s Assistant Project Manager, Megan Bonehilll,  Mob 0400 301 448