Railway Creek Bridge and Trail

December 2014

The construction of the bridge is now complete providing a link from  Power Court to Hampden Road and the new trail to Hurling Drive. The project rebuilt some of the existing trail and provided a new trail connecting to the existing trail network.  Improved signage has also been installed along the trails. 

 

 

September 2014

The construction tender has been awarded to ISCO who have indicated works are expected to commence the week of 10 September 2014 and be completed by early November, subject to favourable weather and no unforeseen circumstances.

Work will include will installation of a steel bridge, two culverts to cross two smaller drainage channels and a rubble surface footpath. 

Should you require any further information or have any queries as works progress:

  • Civil Works Project Manager, Nick Schaschlow, ISCO, Ph 8391 0424
  • Council’s Project Manager, Dave Hutchinson,  Mob 0417 419 952

   

March 2014

At the Council meeting held on 3 March 2014, Council approved the construction of a footpath and bridge over Railway Creek. This will provide a link to the new bridge over the Mount Barker creek and trail along the Steam Ranger rail corridor which is currently in construction.

The project is part of the Trails Master Plan. Awarding of one for one funding from the State Government’s Local Government Stimulus Program has allowed construction of this project to be brought forward.

Railway Creek Location Plan and Concept(474 kb)

Report to Council 4 March 2014 Railway Creek Bridge and Trail(8059 kb) 

The work will be tendered shortly with the aim of completing construction by mid 2014.