Notice of Works - Road Re-sheeting Commencing
| What we're doing: | Council is committed to maintaining all unsealed roads in good condition to ensure a safe and accessible environment for the community. A number of roads have been selected and scheduled for renewal throughout the financial year as part of the ongoing re-sheeting/renewal program. |
|---|---|
| How much is it going to cost: | $1,640,000 |
| Timeframe: | 2026/27 |
| Background: | The scope of works may include tree pruning, drainage improvements, and road surface upgrades. Road markings may be applied to indicate the start and end points of the works, as well as the location of underground services. Driveways will be blended into the new road surface to maintain access to properties. To safely carry out these works, sections of the road may operate with reduced speeds on the days construction is undertaken. During this time, access to driveways may be limited. However, every effort will be made on site to ensure safe vehicle access is maintained during road formation. Council will endeavour to minimise inconvenience to residents and road users. It is recommended that alternative routes be planned while works are underway. Road users are asked to follow any detours and traffic management directions to avoid delays. Council aims to complete the Unsealed Road Re-sheeting/Renewal Program within the current financial year. However, the schedule may be subject to change due to unforeseen circumstances. If this occurs, any affected segments will be rescheduled in a future works program. |
Financial Year 2026/27
The resheeting of unsealed roads across the district is set to commence in the week starting 14 September 2026 (subject to suitable conditions)..
Works may include tree pruning, drainage improvements, and road surface upgrades. Driveways will be blended into the new road surface to maintain access to properties.
To safely carry out these works, sections of the road may operate with reduced speeds on the days construction is undertaken. During this time, access to driveways may be limited. However, every effort will be made on site to ensure safe vehicle access is maintained during road formation.
| Road | Segment |
|---|---|
| Mallawa Road | Dashwood Gully Rd to 1278m south Dashwood Gully |
| Wiles Fire Track | Farmer Rd to 1198m south Farmer Rd |
| Bailey Road | Battunga Rd to Hack Range Rd |
| Hillside Lane | Hender Rd to 417m north Hender Rd |
| Hender Road | Farmer Rd to Hillside La |
| Hender Road | Hillside La to 1242m south Hillside Lane |
| Windsor Avenue | Martin Rd to 637m east Martin Rd |
| Windsor Avenue | 637m east Martin Rd to Easlea Rd |
| Bugle Range Road | Bonython Rd to 1152m south Bonython Rd |
| Bugle Range Road | 1152m south Bonython Rd to Pursell Rd |
| Dunn Road | Bonython Rd to Holder Rd |
| Holder Road | Willcox Rd to Dunn Rd |
| Willcox Road | Bonython Rd to Holder Rd |
| Willcox Road | Holder Rd to Stamps Rd |
| Waters Road | Willcox Rd to 823m east Willcox Rd |
| Chapel Hill Road | Strathalbyn Rd to Diggings Rd |
| Piney Ridge Road | Peggy Buxton Rd to 943m south Peggy Buxton Rd |
| Piney Ridge Road | 943m south Peggy Buxton Rd to 509m north North Rd |
| Military Road | Pyrites Rd to 886m east Pyrites Rd |
| Merritt Road | Native Av to Pinchbeck Ftk |
| Merritt Road | Pinchbeck Ftk to Dunn Rd |
| Archer Hill Road | 83nm east Long Valley Rd to 771m east Long Valley |
| Archer Hill Road | 777m east Long Valley Rd to 1756m east Long Valley Rd |
Financial Year 2025/26
| Road | Financial Year | Status |
|---|---|---|
| Shoulder maintenance in preparation for Resheeting | 2025/26 | Commencing September |
| Jones Road | 2025/26 | Commencing October |
| Military Road | 2025/26 | Commencing October |
| Back Callington Road | 2025/26 | Commencing October |
| Petwood Road | 2025/26 | Commencing October |
| Davis Road | 2025/26 | Commencing November |
| Banksia Road | 2025/26 | Commencing November |
| Nestor Road | 2025/26 | Commencing November |
| Shobrook Road | 2025/26 | Commencing November |
| Blights Reserve Road | 2025/26 | Commencing November |
| Sandow Road | 2025/26 | Commencing November |
| Road | Financial Year | Status |
|---|---|---|
| Razor Back Road | 2024/25 | Complete |
| Hack Range Road | 2024/25 | Complete |
| Liebelt Road | 2024/25 | Complete |
| Sheoak Road | 2024/25 | Complete |
| Military Road | 2024/25 | Complete |
| Bunnett Road | 2024/25 | Complete |
| Schroader Road | 2024/25 | Complete |
| Harvey Road | 2024/25 | Complete |
| Hollows Road | 2024/25 | Complete |