Sealed Roads Resurfacing Program

What we're doing:

Council is committed to maintaining all assets in good condition to provide a safe environment with a number scheduled for renewal during the course of the financial year.

How much is it going to cost:

$4,349,000

Timeframe:2026/27
Background:

Works can include tree pruning or removal, drainage improvements and pavement rehabilitation.  Marks may be painted on the road indicating start and finishing points.  Some roads may also have concrete repairs completed including replacement of kerb and gutter, driveway crossings and spoon drains.

The work will necessitate closing sections of the road for a period of time on the day that construction is undertaken.  During this time there may be limited access to driveway entrances and vehicles should not be left parked on the road.

All endeavours will be made to ensure a minimum of inconvenience, but alternative routes should be planned while these works are under way.  Road users are requested to adhere to any detours that will be in place and plan alternate routes to avoid delay in reaching their destination.

Council endeavours to complete the Sealed Road Renewal Program within the indicated year, however the program can be subject to change due to unforeseen circumstances. If this occurs the affected segment will be scheduled in a future works program.

Financial Year 2026/27

Road
Springs Road East, Mount Barker
Alexandrina Road, Mount Barker
Callington Road, Callington
Cameron Road, Mount Barker
East Parkway, Mount Barker
Exhibition Road, Mount Barker
Hutchinson Street, Mount Barker
Knott Street, Mount Barker
Lilac Parade, Mount Barker
Wellington Road, Wistow

Financial Year 2025/26

RoadSegmentProject Details
Alexandrina Road, Mount BarkerGray Court to Hampden RoadNight works 20 August , asphalt patching
Oborn Road, Mount BarkerAlexandrina Road to Enterprise CourtNight works 19 & 20 August, asphalt patching
Hender Road, WistowHarper Road to Farmer Road18 & 19 August, Asphalt patching followed by spray seal surface renewal
Kondoparinga Road, MeadowsBattunga Road to Clystlands StreetDesign only
Mann Street, Mount BarkerAdelaide Road to Hutchinson StreetCommencing late 2025, night works, asphalt resurfacing and kerbing repair
Wellington Road, WistowLong Valley Road to Bunnett RoadCommencing Sep/Oct, pavement repairs, minor widening, road resurfacing

Financial Year 2024/25

Road

Segment

Status

Project Details

Barker Road, Mount BarkerBluestone Drive to Martin RoadCompleteAsphalt Resurfacing

Bernhardt Crescent, Hahndorf

Full Length

Complete

Road Resurfacing including kerbing repairs

Bray Road, Mount Barker

Waterford Av to Fairfield Rd

Completed

Asphalt Resurfacing

Compson Road, Blakiston

Old Princes Hwy to Alston Rd

Complete

Treatment type to be advised pending design

Crompton Road, Totness

Full Length (excluding cul-de-sac)

Complete

Deep lift Asphalt resurfacing including kerbing repairs

Garwood Court, Littlehampton

Full length

Complete

Asphalt resurfacing including kerbing repairs

Hutchinson Street, Mount Barker

Gawler St to Mann St

Complete

Deep lift Asphalt resurfacing including kerbing repairs

Kennett Street, Meadows

Full length

Complete

Asphalt resurfacing including kerbing repairs

Mace Road, BlakistonBlakiston Road to Rider RoadCompleteAsphalt patching followed by a two coat spray seal

Monks Avenue

Kym Ave to Taramore Cl

Complete

Blakiston Road, Blakiston856m south Downing Road to Nitschke Road

Complete

Asphalt patching followed by a two coat spray seal

Kia Ora Street, Mount Barker

Full length

Complete

Asphalt resurfacing, including the renewal of the kerbing and the footpath on the Northern side

Zanker Drive, Mount Barker

Hurling Drive to Young Street

Complete

Asphalt resurfacing including kerbing repairs

Joseph road, Blakiston

From Clampett Ct to end of Joseph Road

Complete

Asphalt patching followed by a two coat spray seal

Wyndham Road, Blakiston

Full Length

Complete

Asphalt patching followed by a two coat spray seal

Stephen St, Mount Barker

Morphett St to Bonnar Ln

Refer to web link

Refer to Councils web link

Clampett Ct, Blakiston

Full Length

Complete

Asphalt patching followed by a two coat spray seal

Rushton Ct, Littlehampton

From Monks Av to Conifer Ct

Complete

Asphalt Resurfacing

Gumtree Dr, Littlehampton

Smeaton Cres to Edson Cres

Complete

Asphalt Resurfacing including kerbing repairs

Mail Road

To be confirmed

Complete

Asphalt patching, road shoulder maintenance throughout the length of this road to improve drainage and road safety in the coming months. The full road re-surfacing is currently planned to commence April 2025.

Previous Financial Years 2023/24 & 2022/23

RoadSegmentFinancial YearStatusProject Details
Glen Bold Road, Mylor 2023/24CompleteSpray sealing 9 Jan 2024
Canberra Street, Mount BarkerHill Street to Hawthorn Road2023/24CompleteAsphalt resurfacing
North Road, NairneHaeusler Drive to Shetland Court2023/24CompleteDeep lift asphalt resurfacing
To Commence May 2024 over two consecutive Sundays
Currawong Way, Mount BarkerHurling Drive to Ibis Court2023/24CompleteDrainage works 25 Sep 2023
Asphalt resurfacing including the roundabout
Fisher Road, PaechtownFrom Paechtown road for approximately 920m2023/24CompletePatching works and course spray seal - 10 Jan 2024
Gallasch Drive, Mount BarkerFull length2023/24CompleteAsphalt resurfacing
Gilbert Road, Mount Barker 2023/24CompleteAsphalt resurfacing
Hughes Street, Mount BarkerPrinces Road to Hurling Drive2023/24CompleteAsphalt resurfacing
Haeusler Drive, NairneNorth Road to Gabb Court2023/24CompleteAsphalt resurfacing
Scheduled to commence the week of 26 March 2024
Howard Lane, Mount BarkerWellington Road to Howard Close2023/24CompleteAsphalt resurfacing
Joseph Road, BlakistonAlston Road to 568m north Alston Road2023/24CompleteAsphalt patching and spray seal with some rolled bitumen edge in various locations - 10 Jan 2024
West Street, EchungaMarianna Stree to 209m North Marianna Street2023/24CompleteAsphalt resurfacing
Hurling Dr Albert RdRoundabout2022/23CompleteScheduled for 20 to 24 Mar 2023, night works
Barker Rd Hurling DrJunction2022/23CompleteScheduled for 20 to 24 Mar 2023
Walker St, Mount BarkerMorphett St to Gawler St2022/23CompleteScheduled for 24 Mar 2023
night works
Separation Av, Mount BarkerAlberg Av to Faehrmann Av2022/23CompleteScheduled for 16 Mar 2023
Federation Way, Nairne171m south North Rd to Rachel Cct2022/23Deferred 
Bower Road, MeadowsRowley Rd to 539m south Rowley Rd2022/23CompleteScheduled for 15 & 16 Mar 2023
Rowley Rd, Meadowsat junction of Bower Rd2022/23CompleteScheduled for 15 & 16 Mar 2023
Styles St, Meadows 2022/23CompleteScheduled for 14 & 15 Mar 2023
Hagen St, EchungaMarianna St to 162m north Marianna St2022/23CompleteScheduled for 14 & 15 Mar 2023
Charcoal Pit Road, Harrogate 2022/23CompletePatching Saturday 18 Mar 2023
Spray sealing 11 Jan 2024
Mail Road, Harrogatepatching only, will not have spray seal2022/23CompletePatching mid Dec 2022