New Footpath Program

New Footpaths Strategy

Council endorsed the New Footpaths Strategy in 2021 consisting of an $11 million investment over 10 years and supported the development of a detailed program of works.

Identification of new footpath locations have been informed through collating outcomes of the township planning consultations, customer requests, conversations with community groups, internal consultation and the annual business plan feedback.

New footpaths are prioritised upon the following endorsed criteria:

  • Traffic impact - determined through the volume and type of traffic using the road the path is to be adjacent.
  • Accessibility - the construction of a path will provide linkages to pedestrian generators and attractors such as community facilities, schools, aged care facilities, tourist facilities, residential areas, and shopping precincts.
  • Demand - where there is evident demand and a positive impact on the network.
  • Connectivity - connection to the existing footpath network through the construction of missing footpath links, or the creation of desired walking loops or walking destinations.

The program is comprised of two stages: planning and design; and construction of new footpaths.

The investment into new footpaths and the coming year's program is reviewed each year as part of the development of the annual business plan and budget.  Refer to the table below for the latest on design, construction and footpaths included for the year.

The work will necessitate closing sections of the road for a period of time on the day that construction is undertaken.  During this time there may be limited access to driveway entrances and vehicles should not be left parked on the road.

September 2026

English Street and Molens Road Hahndorf new footpaths are included in the 2025/26 New Footpath Program (see below).

Project: Construction of Footpath along Molens Road (East side from Balhannah Road to English Street)

Construction of Footpath along English Street (Northern side between Molens Road and Collins Street)

Work Starting: 12 October

Work period: Until end November (subject to weather conditions and contractor confirmation)

Mon to Friday- 7:00am to 5:00pm

Traffic arrangements: Detour around work area on Molens Road. Reduced Speed limit restrictions will apply and road users are requested to observe work zone traffic Management in place when travelling through the area.

Contractor: Tarra Civil Pty Ltd.

2028/29Proposed Footpaths
ActivityFootpathSegmentTownship

Construction

Ambleside Road

Mount Barker Road to Ambleside Service Road

Hahndorf

Construction

Woodside Road

Joanne Street to Rachel Circuit

Nairne

Construction

Mine Road

Princes Highway to Bike Park

Kanmantoo

2027/28Proposed Footpaths
ActivityFootpathSegmentTownship

Construction

Mount Barker Road

50m east Caravan Park to River Road

Hahndorf

Construction

Springs Road

Waterford Avenue to Wetland Pedestrian Crossing Springs Road

Mount Barker

Construction

Memorial Drive

Bollen Road to Maurice Road

Mount Barker

Construction

Angus Road

Sophia Street to High Street

Echunga

Design

Ambleside Road

Mount Barker Road to Ambleside Service Road

Hahndorf

Design

Mine Road

Princes Highway to Bike Park

Kanmantoo

ConstructionWoodside RoadWebber Drive to Joanne StreetNairne

Financial Year 2026/27

ActivityFootpathSegmentTownship

Design

Mawson Road

30m east Nottage Road to Expedition Boulevard

Meadows

Construction

Callington Road

Recreation Grounds Entrance to North Terrace (includes School Crossing) (both sides of road)

Callington

Design

Mount Barker Road

50m east Caravan Park to River Road

Hahndorf

Construction

North Road

Clydesdale Place to Woodside Road

Nairne

Design

Springs Road

Waterford Avenue to Thornbill Drive

Mount Barker

Design

Angus Road

Sophia Street to High Street

Echunga

Design, ConstructionFormer Quarry TrailBluestone Estate, Martello Avenue to Silhouette with extension to Crawford WalkMount Barker
ConstructionMemorial Drive Bollen Road to Maurice  RoadMount Barker
Construction Bald Hills Road Scarborough Way to at Grade Pedestrian Crossing adjacent Bald Hills Road/Wetland CulvertMount Barker
ConstructionWoodside RoadByethorne Park to Webber DriveNairne
DesignWoodside RoadWebber Drive to  Rachel CircuitNairne
2025/26
FootpathSegment
Bartley Street, Nairne Stage 2B

Construction - Edenborough Street to rear Hills Family Church (includes Railway Maze - subject to ARTC approvals)

Woodside Road, NairneConstruction - Pedestrian Refuge to Woofside Dog Park (Webber Drive)
Molens Road, HahndorfConstruction - Balhannah Road to English Street
English Street, Hahndorf

Construction - Molens Road to opposite Collins Street

Bald Hills Road, Mount Barker

Construction - Scarborough Way to at Grade Pedestrian Crossing adjacent Bald Hills Road/Wetland Culvert

Princes Highway, NairneConstruction - Frontage 18 Princes Highway
Mawson Road, MeadowsDesign - 30m east Nottage Road to Expedition Boulevard
North Road, NairneDesign - Clydesdale Place to Woodside Road
Woodside Road, NairneDesign - Webber Drive to Rachel Circuit
2024/25
FootpathSegmentFinancial YearStatusComment
Bartley Street, Nairne (Stage 2)Edinborough Street to Old Princes Highway2024/25In progress 
Sydney Road, NairneNorth Road to Allon Place2024/25In progressConstruction estimated July 2025
North Road, NairneJunction Street to Bridge Street2024/25In progressConstruction estimated July 2025
North Road, NairneHaeusler Dive to Clydesdale Place2024/25In progressDesign in 2026/27.
North Road, NairneJunction Street to William Street2024/25DeferredRequires potential land acquisition.
Woodside Road, NairneByethorne Park to Webber Drive2024/25In progressCurrently in design.
Junction Road, LittlehamptonRoundabout to Benjamin Grey Drive2024/25In progressAwaiting delivery of pedestrian bridge
Callington Road, CallingtonMurray Street to Recreation Park2024/25In progressCurrently in design
Molen Road, HahndorfBalhannah Road to English Street2024/25In progressCurrently in design for construction in 2025/26.
English Street, HahndorfMolen Road to Collins Street2024/25In progressCurrently in design for construction in 2025/26.
Linear Trail, Mount BarkerFrom Railway bridge to Alexandrina Road2024/25CompleteInstallation of new asphalt surface to this trail segment along with minor vegetation improvements
FootpathSegmentFinancial YearStatusProject Details
Bartley Street, Nairne (Stage 2)Edinborough Street to Old Princes Highway2023/24To commenceDesign
Sydney Road, NairneNorth Road to Allon Place2023/24Complete 
North Road, NairneJunction Street to Bridge Street2023/24In progressDesign in progress, construction late 2024
Woodside Road, NairneByethorne Park to 34 Woodside Road2023/24To commenceConstruction early 2024
South Terrace, NairneMarket Place to 22 Princes Highway2023/24In progressPartially complete. Remining section in design, construction TBA
North Road, NairneHaeusler Drive to Clydsdale Place2023/24To commenceConstruction mid 2024
Junction Road, LittlehamptonRoundabout to Benjamin Gray Drive2023/24In progressDesign
Callington Road, CallingtonMurray Street to Recreation Park2023/24In ProgressDesign
North Road, NairneJunction Street to William Street2023/24In ProgressDesign
Wellington Road, Mount BarkerRailway Terrace to Victoria Road2023/24CompleteNew concrete footpath and associated stormwater pipe repairs along the southern side of the road (same side as IGA) between Railway Terrace and Victoria Road
Old Princes Highway, NairneChestnut Drive to woodside Road2023/24Complete 
Luck Street, MacclesfieldVernon St to Devereux St2022/23 - 2023/24Complete 
Bartley Street,
Nairne (Stage 1)
Matthew Smilie Drive to Edinborough Street2022/23 - 2023/24In progress

Stage 1 construction (between Britannia Road and Edinborough Street) - during construction a previously unidentified SA Water water main was found with SA Water to complete remedial works before the footpath construction can recommence.

Complete
Church Hill Road, EchungaAdelaide Rd to Gratwick St2022/23CompleteNew footpath to northern side, Adelaide Road to Gratwick Street
Flaxman Avenue, MeadowsMill St to Mawson Rd2022/23CompleteNew footpath to entire eastern side.
Davies Street, MacclesfieldKingrose St to Marriott St2022/23CompleteNew footpath and kerb to eastern side
Venables Street, MacclesfieldTodd Street to Marriott2022/23CompleteNew footpath to western side
Marriott Street, MacclesfieldVenables Street to Davies Street2022/23CompleteNew footpath to northern side

Background

In 2021, Council was presented the methodology for prioritising new footpaths which includes traffic impact, accessibility, demand and connectivity. The proposed new footpaths program for the next four years (2021/2022 to 2024/25, current as at 2021) was listed in the presentation.

New Footpath Presentation December 2021

This of course all has to be balanced with new resident's expectations of city amenities with retaining the natural beauty and quirks of living in the beautiful hills.