Heysen Boulevard Level Crossing Design and Construction

What we’re doing

Design of railway level crossing on the Heysen Boulevard to link up the Minters Field and Bluestone development which will provide a connection between Barker and Wellington Roads.

How much it is going to cost

$2,500,000

Timeframes

2022/23 & 2023/24

Background

Negotiations with State Government are completed.

The Progress

Progress updates will be reported via the Department for Infrastructure and Transport Website:  Heysen Rail Crossing Project

On Monday 8 January 2024, early works will be commencing on the Heysen Boulevard rail crossing project.  The early works will include removal of the rail and ballast, installation of underground services for electrical and wastewater together with some general site works and then replacement of the rail.  This will all occur over the next few months whilst the Steam Ranger is not operating in Mt Barker.

The construction of the rail signalling and road will occur once design is completed with target date for completion of construction in the second half of 2024.