Interchange Shelters
What we’re doing
Supply and installation of interchange shelters for the football sports field at the Summit Sport and Recreation Park.
How much it is going to cost
$85,000
Timeframes
Scheduled for completion by the end of November 2022.
The Progress
Works have been completed.
The design of the shelters is in accordance with AFL Preferred Facility Guidelines, Section 2.5, Regional.
Photo: progress of the assembly of one of the shelters.