Projects

Springs Wetland Trail Head

What we’re doing

Completing the landscaping alongside Springs Wetland and Pavilion to create a new entrance for the wetlands and trail head for the popular Laratinga Trail.

How much it is going to cost

$43,000

Timeframes

2022/23 financial year

The Progress

In progress

Background

Footpath and landscaping complete. Shelter and furniture to be completed in February 2023.

Duck Flat Creek Trail

What we’re doing

Shared path along drainage reserves associated with Duck Flat Creek, linking Laratinga Wetlands share path network.

How much it is going to cost

$55,000

Timeframes

2021/22 and 2022/23 financial year

The Progress

This has now been completed and open to the public.

The pedestrian crossing at Alexandrina Road is scheduled to commence from 28 June and be complete by end of July.  Please look out for changed traffic conditions during construction and pedestrians crossing the road when works are complete.

Works are progressing well, despite the wet weather and are on track to be complete by end of June 2022.

The trail works for the Duck Flat Creek Trail project will begin in early May with compound setup, followed by construction.

The project is anticipated to take 4 weeks.

The red sections on the maps indicate the trail to be constructed.